Aurora Kilpilahti: EPC delivery of a new substation

Project details

  • Facts

    Aurora Kilpilahti is part of Aurora Group. The Kilpilahti business area is an important hub for circular economy in the Nordic region. Rejlers has been reliable engineering partner for Aurora for many years.​

  • What we did

    During the project, new transformation substation building was built. Rejlers delivered electricity distribution network to a part of Kilpilahti industrial area. At the same time, the structure of the network was changed to meet today’s requirements. ​

  • Highlight

    “Aurora’s key requirement is to maintain high availability here in the area and to operate cost-effectively, delivering the service that our customers need. Rejlers has produced good results in terms of schedule, cost and project scope.​” – Jyrki Havukainen, Site Manager, Aurora Infrastructure​

Watch the whole customer case story

Case on YouTube

Content can't be viewed

To view content, you must accept marketing cookies.

EPC (engineering, procurement and construction) delivery of a new substation serving hydrocarbon unloading terminal at Aurora Kilpilahti, Finland.​ Contract included groundworks, the building itself and all electrical equipment required for electricity distribution, installed, tested and ready for commissioning.

Get in touch

Have a question?

Samuli Kyttälä Head of Industry, Finland